REDUCED INJECTION DUE TO CONSTRUCTION WORK IN THE TRANSMISSION SYSTEM

FROM 20/11-2023 TO 28/1-2024 (70 DAYS)

Dear Storage Customer, GSD would like to draw your attention to UMM ID 23092510X1001A1001A248001, announced on 25/9-2023 by Energinet.

Please note that the announced construction work on the pipelines in the western part of Funen will affect GSD’s ability to inject natural gas in a period of 70 days starting from gas day 20/11-2023.

During that period the available injection capacity will be reduced by 508 MW – from the maximum rate 3,780 MW to 3,272 MW. The reduced injection capacity is expected back online starting from gas day 29/1-2024.

GSD would like to stress that the already booked firm injection capacity will not be affected by the reduction.

If you have any questions, please do not hesitate to reach out.

 

CHECK OUT the NEWEST INFORMATION

UPDATED ANNOUNCEMENT

REVIEW DIAGRAM

AVAILABLE CAPACITY

SUBSCRIBE TO NEWS

Receive notifications directly by e-mail