UPDATE on REDUCED INJECTION due to CONSTRUCTION WORK in the TRANSMISSION SYSTEM

NEW PERIOD FOR REDUCTION 6/11-2023 TO 15/12-2023 (39 DAYS)

With reference to our earlier announcement, please note that UMM ID 23092510X1001A1001A248001, announced on 25/9-2023 by Energinet has been updated on 24/10-2023.

The announced construction work on the pipelines in the western part of Funen will be carried out within a shorter period of 39 days starting on 6/11-2023 and ending on 15/12-23, both days included.

During that period the available injection capacity will be reduced by 508 MW – from the maximum rate 3,780 MW to 3,272 MW. The reduced injection capacity is expected back online starting from gas day 16/12-2023.

GSD would like to stress that the booked firm injection capacity will not be affected by the reduction.